PROJECT LOCATION: 30 Crown Place
PROJECT DESCRIPTION: M&E service alterations
PROJECT DURATION: 14 weeks

The scope:

Platinum Facilities was appointed by a long-standing client to manage alterations to the building M&E Services, to allow the creation of an agile working environment. The project was across 6 working floors and was completed in 2 phases, each phase consisting of around 5 weeks out of normal working hours

  • Mechanical & Electrical isolation, decommissioning and strip out of services.
  • New services installed to new open plan work space and collaboration spaces created.
  • Public health modifications.
  • Modifications to FCU’s ductwork on the landlord’s systems
  • Commissioning & testing.
  • O&M documentation & record drawings.
  • New sprinkler and power installation to bespoke meeting PODs.
  • Fire alarm modifications to suit new office layout.

Share this post

London Head Office
1 George Yard
City of London
England
EC3V 9DF

0207 977 5650
E: info@pfms.co.uk

West Farm House
Cams Hall Estate
Fareham
Hampshire
PO16 8UT

0207 977 5650
E: info@pfms.co.uk

PURE Offices
1 Devon Way
Longbridge Technology Park
Birmingham
B31 2TS

0207 977 5650
E: info@pfms.co.uk

Agile Working case study